Legal
Ann Wright: Insolvency isn’t always a get-out
Ann Wright FCIOB
Case: Selby Hall & Philip Shivers v Jan Van Der Heiden
Technology and Construction Court, March 2010
It was a simple £143,000 flat refurb. Ms Hall and Mr Shivers hired an architect and signed a JCT Minor Works contract with Mr Heiden, the builder. Work was to start on 21 May 2008 and finish on 22 September. If the builder was late he faced liquidated damages at £700 a week.
By August the claimants, who were in rented accommodation, were anxious about completion. Then Mr Heiden took an unscheduled fortnight’s holiday. On his return he said he would be five weeks late but did not claim for extension of time.
In December, the kitchen and bathroom were still incomplete and defective lighting and flooring and missing joinery were noted. In January Mr Heiden was asked for a completion programme. He responded with a claim for a 10-week extension. Two days later he said the works had reached practical completion. Mr Fletcher, the architect, refuted Mr Heiden’s claims with a list of outstanding works and reasons why the claim was excessive.
The builder’s cash flow had not been restricted. The claimants agreed to pay in advance of the architect’s interim certificates. Until December Mr Heiden had been overpaid and by 8 January 2008 the claimants had paid all sums Mr Fletcher had certified.
On January 7 and 9 Mr Heiden issued an interim application for £170,000. Mr Fletcher replied that the figures were overstated; that Mr Heiden was only entitled to a six-week extension and that liquidated damages would apply from 3 November.
Mr Heiden suspended work on 21 January. After an attempt at mediation failed, Mr Fletcher and the claimants’ solicitors gave Mr Heiden written notice to finish the job. He refused and on 12 March the solicitors determined his contract under clause 6.4.2.
It took replacement contractors until 17 May 2009 to achieve practical completion. Ms Hall and Mr Shivers claimed £56,891.27 for the work plus £20,300 for liquidated damages.
Mr Heiden made a statement in December 2009, but failed to respond to the judge’s directions in February 2010. On 5 March he sacked his legal team. On 10 March, he told the claimants’ solicitors that Rod Jones of Glaiston Jones would act for him. It turned out Mr Jones was an insolvency practitioner.
At 9.30am on the last working day before the hearing, Mr Jones faxed that he was applying for an interim order under section 252 of the Insolvency Act and all legal proceedings must cease. In the afternoon, he faxed that the order had been made in Swindon County Court, so that court would have full control of the situation.
At a hearing on 15 March, the TCC judge decided otherwise and generally found for the claimants.
Analysis
In cases of insolvency, legal proceedings usually cease, other than in the court dealing with the insolvency.
Although Mr Heiden was not present or represented in the court hearings, the judge considered his position based on Mr Jones’ faxes, Mr Heiden’s statement and his QS’s report.
On the jurisdiction argument, the judge found he could continue with the case. He said the insolvency application was a “manipulative, last-minute, high-stakes attempt to avoid the consequences of a [court hearing]” and would encourage those in a “parlous financial state” to wait until the last working day to achieve adjournment of a High Court trial without financial penalty.
In the hearing itself, the judge was careful to ensure Mr Heiden’s point of view was represented, quoting from his statement. This shows both that the insolvency of one party may not be a bar to continuing with the case and the non-appearance of a defendant does not mean the claimant has a walk-over.
Ann Wright FCIOB is an adjudicator and quantity surveyor.
T: 01675 466009
Ann Wright is planning to retire shortly. Would you be interested in contributing to Case notes? Please email elaine@atompublishing.co.uk
Leave a comment
Construction Pro
Is commercial property a Deal breaker?
Concerns have been voiced over how the much-vaunted Green Deal will stack up when it comes to commercial buildings. Denise Chevin reports Will the Green deal work for commercial property? ...
» Read full articleGet your head round mental health
Mental health is one of the biggest problems facing businesses today. Yet, as Jamie Patterson explains, the issues are often ignored. Mental health conditions were the most common cause of ...
» Read full articleFive things… you ought to know about energy consumption in the home
01 We spend more on electricity than gas We use three times as much gas as electricity — but electricity costs more than three times as much, so on average ...
» Read full articleGarry Winter’s case notes
Thameside Construction Company v Arthenella Technology and Construction Court 20 October 2011. Thameside was employed by Arthenella to undertake the conversion of Frogmore Hall in Hertfordshire into residential units. The ...
» Read full article
Five ways to… survive the office Christmas party
01 Time your arrival You don’t want to be the first to turn up… or the last, so check you know the itinerary for the evening. Being “fashionably late” might give ...
» Read full article
When actions speak louder than words
Your attitude and the way you communicate on site will have more influence on health and safety outcomes than a rule book written in the office, argues Glen Robertson On ...
» Read full articlePeter Stockill’s Case notes
Witney Town Council v Beam Construction (Cheltenham) Technology and Construction Court 2011 If you start an adjudication, you naturally want to be confident that the decision will be enforced. Under ...
» Read full articleThe right to imply
Two recent cases show that goods and services should be fit for purpose, even where there is no contract, says James Mullen In July 2011 two judgments considered terms being ...
» Read full article
Out with the old...
Changes to the Building Regulations and Building Control are afoot. Paul Everall explains what they mean for construction firms. The next few months might be an interesting time for those ...
» Read full articleStephen Clarke's case notes
James Andrew Robinson v PE Jones Court of Appeal, January 2011 In December 1991 Mr Robinson agreed to buy a new-build house from PE Jones (Contractors) (“the contractor”). During construction ...
» Read full article (1 comment)Five words you’ve heard…but were afraid to ask what they meant
01 Annular nail A nail with ridges along its shaft that help hold it firmly in place and prevent the nail pulling out. Often used for fixing plywood and other similar ...
» Read full article
Temps have rights now too you know
The Agency Workers Regulations become law this year. Christopher Syder and James Pike explain what they mean for construction firms. As some construction businesses begin to see an upturn in demand, ...
» Read full article (1 comment)Garry Winter’s case notes
Inframatrix Investments v Dean Construction Technology and Construction Court, 25 July 2011 Inframatrix ("Infra") wanted to build a camera factory. Dean was the contractor for the cladding and roofing works. ...
» Read full article
Just when you thought you’d got to grips with the Construction Act...
Changes to the Construction Act are due to come into force later this year and, as Stephen Clarke explains, they should not be underestimated by any party to a contract ...
» Read full articleRichard Hildrick’s Case notes: July/August 2011
CRJ Services v Lanstar Technology and Construction Court, 19 April 2011 Lanstar was the operator of a waste management and recycling facility near Salisbury in Wiltshire. Since 2007 Lanstar had ...
» Read full articleIt’s localism, but not as we know it
New development to drive the economy is overshadowing localist agendas. But Joanne Cave argues there’s room for both As the Localism Bill makes its passage through Parliament, it has attracted ...
» Read full articleFive ways to… improve agency recruitment
...improve agency recruitment 01 Plan ahead Making an agency aware of your requirements several weeks in advance will allow it to find, interview and screen local candidates well in advance of ...
» Read full article
The disability that’s coming out of hiding
Thousands of employees could be suffering from dyslexia without knowing it. But the condition is now gaining more recognition. Denise Chevin reports. Simon Hodges left school at 16. He had ...
» Read full articleFive ways to… make the most of living walls
01 Don’t be put off by the challenges of the building Living walls can go anywhere, at any height, with any aspect or level of exposure — it’s all about ...
» Read full articleRob Horne’s Case notes: June 2011
Jones v Kaney Supreme Court 2011 Most of us would not give a second thought to the consequences of someone we had asked for advice giving that advice negligently. We would ...
» Read full articleFive ways to...
Five ways to… get your green mojo back... and keep it 01 Find someone to inspire you There are plenty of green superheroes out there. Anita Roddick, Bill McKibben, Paul Hawken, Ray ...
» Read full articleInsurance at a premium
Contractors will find bonds harder to come by and the cost of professional indemnity insurance is set to rise, report David Hayhow and Jake Tobin The construction market remains slow ...
» Read full articleRefurbishment did not create a new dwelling
Court rules that couple cannot claim for defective work under the Defective Premises Act. Ben Worthington explains Builders and design consultants involved in housebuilding or refurbishment works will be interested ...
» Read full articlePaul Lomas-Clarke’case notes
De Beers UK v Atos Origin IT Services UK Technology and Construction Court 2011 Construction contracts are awash with disputes about the responsibility for delays and liability for damages. The ...
» Read full article
Measuring up to the carbon challenge
Demonstrating your sustainable credentials is easier said than done, given the number of different standards out there. But there is an alternative, says Kye Gbangbola What’s the best approach for ...
» Read full article
Green Deal’s gender agenda
Meeting carbon targets will create openings ideally suited to women, says Niki Luscombe — as long as we can train them first “Transforming the built environment to low carbon could ...
» Read full articleRichard Hildrick’s Case notes: McCain Foods GB v Eco-Tec (Europe)
McCain Foods GB v Eco-Tec (Europe) Technology and Construction Court, January 2011 In 2008, McCain entered into a £263,500 contract with Eco-Tec, which was to provide a process engineering system ...
» Read full article (1 comment)
Why we specified... April 2011
Cast in situ concrete sawtooth roof by Shepherd Construction Loughborough University Design Centre Nicholas Burwell, partner, Burwell Deakins Architects The Loughborough University Design Centre is a £15M project to construct ...
» Read full article
Why we specified...Mar11
SolarTech Renewable Energy Solutions Code Level 6 homes at Mendip Place, Chelmsford Jason Page, assistant architect, Ingleton Wood Architects At Mendip Place, six houses and four flats for local housing ...
» Read full articleGarry Winter’s Case notes – Co-operative Group v John Allen Associates
Technology and Construction Court 2010 John Allen Associates (JAA) was a consulting engineer which, while employed initially by developers, had also provided a warranty to the overall client, the Co-operative ...
» Read full articleKeeping BIM on the right side of the law
The adoption of multi-party BIM models will need careful legal underpinning. CM asked law firms Brodies and Fenwick Elliott for their views Does sharing data mean sharing liability? BIM carries on ...
» Read full articleEnvironmental markets: more detail on Defra's plans
ONLINE ONLY Bio-diversity offsetting looks like it could be arriving in the UK, following the trend in many countries to use “environmental markets” to protect natural habitats. In 2008 in the United States, conservation credits from developers raised over $3bn for wetland conservation.
» Read full article
Will pricing our wildlife ease planning pain?
The government has drawn up a proposal to let developers buy their way out of on-site biodiversity measures. Denise Chevin reports
» Read full article (1 comment)Richard Hildrick’s Case notes: February '11
Straw Realisations, formerly known as Haymills (Contractors) (in administration) v Shaftsbury House (Developments) Technology and Construction Court, October 2010 Haymills was the contractor for an £8.5m mixed-use development in Islington, ...
» Read full articleLegal update: Localism Bill explained
ONLINE ONLY By Michael Hardware of Chelgate, public relations and public affairs consultants Following much speculation as to its content, the Decentralisation and Localism Bill was finally introduced to the House of ...
» Read full articleAlisdair Matheson's Case notes: Jan '11
Dhamija & another v Sunningdale Joineries & others Technology and Construction Court, October 2010 In 2009 Mr and Mrs Dhamija pursued their contractor Sunningdale Joineries, along with their architects and ...
» Read full article (1 comment)Peter Jacobs: And about time too
Peter Jacobs, CIOB vice-president, and until recently delivery director at the 2012 Olympic Village, reviews the CIOB’s new protocol on time management. Keith Pickavance is a recent Past President of ...
» Read full article (1 comment)
Specialist cover that could be a life saver
An insurance policy that acts as an alternative to subcontractor bonds has proved popular in the US and could take off here. Elaine Knutt reports For main contractors reading the ...
» Read full article (1 comment)A tough examination
This month, two readers are concerned about the tough jobs market, despite studying to improve their chances. Our Career Consultants offer their tips. Q I am a part-time HNC Construction ...
» Read full article (3 comments)Richard Hildrick's Case notes: Nov/Dec10
How Engineering Services v Southern Insulation (Medway) Technology and Construction Court, July 2010 How Engineering was the M&E subcontractor to Sir Robert McAlpine on the development of an office building in ...
» Read full articleGarry Winter’s Case notes
Traditional Structures v H W Construction Technology and Construction Court, May 2010 H W Construction was tendering as main contractor for a business development centre. Part of the project required ...
» Read full article (1 comment)
‘Green’ clauses — the new ties that bind
As energy targets become linked to clients’ cold, hard cash, there’s a risk that new areas of loss and litigation could open up, warns Brad Fearn In our recent survey ...
» Read full articleRichard Hildrick’s Case notes
Case notes Case: WW Gear Construction v McGee Group Technology and Construction Court June 2010 WW Gear was the developer and employer for the Westminster Plaza Hotel in London. McGee ...
» Read full article (2 comments)
There’s a cloud coming your way
Outsourcing software and computer services is increasingly being seen as a cost-effective and sustainable IT option. Graham McLean advises Cloud computing is causing major shifts in the IT industry, and ...
» Read full articleCareer Consultant: What price experience?
Advice for an experienced manager who has found that a post-graduate qualification hasn’t boosted his prospects Q. I have been working in the construction industry for more than 30 years, ...
» Read full article (3 comments)Ann Wright: Computer calamity
Ann Wright’s Case notes Computer calamity Case: Kingsway Hall Hotel v Red Sky (Hounslow). Technology and Construction Court May 2010 In 2006 the Kingsway Hall Hotel paid £49,999 plus an ...
» Read full article (1 comment)Ann Wright: Summary execution
Case: Clancy Consulting v Derwent Holdings, Anglo International Holdings, Mardown, Cashtal Properties, Mount Murray Country Club and Cashtal Developments. Technology and Construction Court March 2010. The defendants were separate companies, ...
» Read full articleDo project managers make good business leaders?
A seat on the board requires different skills from project management, says Mace’s Brian Moone Excel long enough as a project manager and you may be invited to join the ...
» Read full articleAnn Wright: Insolvency isn’t always a get-out
Case: Selby Hall & Philip Shivers v Jan Van Der Heiden Technology and Construction Court, March 2010 It was a simple £143,000 flat refurb. Ms Hall and Mr Shivers hired ...
» Read full articleBaby on board
CM readers know how to manage projects, but managing your career can be a lot trickier. So we’ve assembled our panel of experienced Career Consultants to offer a fresh perspective. ...
» Read full article (2 comments)
Learning the lessons on green education
Institutions are only gradually addressing the gap in sustainable learning. Katie Puckett reports Buildings are getting more complex, regulations are tighter, and it’s increasingly down to the contractor to deliver a ...
» Read full article (6 comments)To avoid legal claims and lost tenders – read on
Under the Equality Bill, it’s time to even up pay and opportunity for everyone, writes Sharon Latham In its manifesto ahead of the 2005 general election, the Labour Party committed ...
» Read full articleAnn Wright: Questions of probability
Case: Speymill Contracts v Eric Baskind Court of Appeal February 2010 Raby House in Cheshire used to be a hotel. Sometime before 2005, it was bought by a Mr Baskind to ...
» Read full article
Get ready for next round in contractual paper chase
The new Construction Act may be on hold, but Hamish Lal says it cannot be ignored. What is the new Construction Act? When does it take effect? How will it ...
» Read full article (2 comments)The time is ripe for a new approach to insurance
At present, many contractors purchase a standard package of insurance products, regardless of the type, size, location and duration of the project. Often there are overlaps and inefficiencies with this ...
» Read full articleAnn Wright: A step in the wrong direction
Case: Thomas Henry Jose and MacSalvors Plant Hire Ltd v Brush Transformers Ltd. Court of Appeal 15 December 2009 Mr Jose, a competent and experienced crane driver, worked for plant ...
» Read full article (1 comment)
Clampdown on the framework fiddlers
New regulations have been introduced to give contractors more remedies to deal with uncompetitive practices. Peter Gracia reports After the Office of Fair Trading revelations last year that price fixing ...
» Read full articleAnn Wright: Called to account
Jim Ennis Construction Ltd v Combined Stabilisation Ltd TCC 20 November 2009 From 2008, CSL carried out groundworks for JEC at Bovis Lend Lease’s site at Unity College, Burnley. CSL’s ...
» Read full articleLegal: Blowing the whistle on construction disputes
Legal advisers suggest a range of tactics contractors can deploy to avoid or defuse disputes Many CM readers will probably have experienced the horrors of a construction dispute – if not first-hand, they’re ...
» Read full article (1 comment)


