Legal
Ann Wright: Questions of probability
Case: Speymill Contracts v Eric Baskind
Court of Appeal February 2010
Raby House in Cheshire used to be a hotel. Sometime before 2005, it was bought by a Mr Baskind to convert into his home. Speymill was selected as the contractor and work began in August 2005.
The contract was in writing and confirmed that the JCT Standard Form 1998 Private Without Quantities would apply. However, no formal contract document was signed.
As the job progressed, architect JSD issued 15 interim payment certificates, amounting to £753,490.44.
The last of these was issued on 12 October 2006. JSD also issued the practical completion certificate on 27 June 2006 and asked for an extension of time.
Mr Baskind paid certificates one to 11 in full. But on 12 April 2006 he only paid part of certificate 12 and did not pay the remaining certificates. In total, he paid Speymill £652,786.20.
Following months of negotiation over the bill, Speymill went to adjudication on 28 November 2008. Mr Baskind said he had issued several withholding notices against certificates 12 to 15. Speymill said it had not received any of these notices.
When Mr Baskind was asked to produce copies of his withholding notices, he could not, and claimed that in September 2006 two of Speymill’s employees had stolen some of his files, which had included his copy notices.
Mr Baskind then said he could not produce any electronic records as a lightning strike and power surge in October 2006 had destroyed his computer records.
Speymill denied that it had taken any of Mr Baskind’s documents or that it had received any withholding notices from Mr Baskind directly or from his professional team.
The adjudicator decided that allegations of theft were a criminal matter and outside his jurisdiction. However, he noted that Mr Baskind had failed to prove, on the balance of probabilities, that he had issued effective withholding notices.
The adjudicator decided that Mr Baskind should pay Speymill £427,737. When he did not pay, Speymill tried to get the adjudicator’s decision enforced by summary judgment (a quick procedure where the court only has to decide whether or not the defendant has an arguable defence to the action).
Although the judge had reservations about the strength of Mr Baskind’s defence, he conceded that it was at least arguable and refused summary judgment.
Speymill appealed. The Court of Appeal noted that it was unusual for the professional team not to have copies of the withholding notices and that Mr Baskind could produce nothing. The court allowed the appeal.
Analysis
Normally, there is no statutory right to adjudication for projects on owner-occupied homes. The inclusion of the JCT contract in this case, however, introduced adjudication as a contractual right.
In all civil legal forums, assertions have to be backed with proof “on the balance of probabilities”.
This is harder than it seems. For example, many discussions and phone calls are not witnessed by others. If disputed at a later date, proving what was actually said can be problematic.
Mr Baskind’s chain of circumstances meant that he could not prove he had sent withholding notices. As a result, he failed to prove he had a case for withholding payment, although the adjudicator and courts were careful to not comment on the alleged theft. That was for the criminal courts.
However, the judgment was stayed – ie put on hold – pending the resolution of other financial matters in dispute, so no payment was actually made to Speymill.
Ann Wright FCIOB is an adjudicator and quantity surveyor.
T: 01675 466009
Ann Wright is planning to retire shortly. Would you be interested in contributing to Case notes? Please email elaine@atompublishing.co.uk
Leave a comment
Construction Pro
Is commercial property a Deal breaker?
Concerns have been voiced over how the much-vaunted Green Deal will stack up when it comes to commercial buildings. Denise Chevin reports Will the Green deal work for commercial property? ...
» Read full articleGet your head round mental health
Mental health is one of the biggest problems facing businesses today. Yet, as Jamie Patterson explains, the issues are often ignored. Mental health conditions were the most common cause of ...
» Read full articleFive things… you ought to know about energy consumption in the home
01 We spend more on electricity than gas We use three times as much gas as electricity — but electricity costs more than three times as much, so on average ...
» Read full articleGarry Winter’s case notes
Thameside Construction Company v Arthenella Technology and Construction Court 20 October 2011. Thameside was employed by Arthenella to undertake the conversion of Frogmore Hall in Hertfordshire into residential units. The ...
» Read full article
Five ways to… survive the office Christmas party
01 Time your arrival You don’t want to be the first to turn up… or the last, so check you know the itinerary for the evening. Being “fashionably late” might give ...
» Read full article
When actions speak louder than words
Your attitude and the way you communicate on site will have more influence on health and safety outcomes than a rule book written in the office, argues Glen Robertson On ...
» Read full articlePeter Stockill’s Case notes
Witney Town Council v Beam Construction (Cheltenham) Technology and Construction Court 2011 If you start an adjudication, you naturally want to be confident that the decision will be enforced. Under ...
» Read full articleThe right to imply
Two recent cases show that goods and services should be fit for purpose, even where there is no contract, says James Mullen In July 2011 two judgments considered terms being ...
» Read full article
Out with the old...
Changes to the Building Regulations and Building Control are afoot. Paul Everall explains what they mean for construction firms. The next few months might be an interesting time for those ...
» Read full articleStephen Clarke's case notes
James Andrew Robinson v PE Jones Court of Appeal, January 2011 In December 1991 Mr Robinson agreed to buy a new-build house from PE Jones (Contractors) (“the contractor”). During construction ...
» Read full article (1 comment)Five words you’ve heard…but were afraid to ask what they meant
01 Annular nail A nail with ridges along its shaft that help hold it firmly in place and prevent the nail pulling out. Often used for fixing plywood and other similar ...
» Read full article
Temps have rights now too you know
The Agency Workers Regulations become law this year. Christopher Syder and James Pike explain what they mean for construction firms. As some construction businesses begin to see an upturn in demand, ...
» Read full article (1 comment)Garry Winter’s case notes
Inframatrix Investments v Dean Construction Technology and Construction Court, 25 July 2011 Inframatrix ("Infra") wanted to build a camera factory. Dean was the contractor for the cladding and roofing works. ...
» Read full article
Just when you thought you’d got to grips with the Construction Act...
Changes to the Construction Act are due to come into force later this year and, as Stephen Clarke explains, they should not be underestimated by any party to a contract ...
» Read full articleRichard Hildrick’s Case notes: July/August 2011
CRJ Services v Lanstar Technology and Construction Court, 19 April 2011 Lanstar was the operator of a waste management and recycling facility near Salisbury in Wiltshire. Since 2007 Lanstar had ...
» Read full articleIt’s localism, but not as we know it
New development to drive the economy is overshadowing localist agendas. But Joanne Cave argues there’s room for both As the Localism Bill makes its passage through Parliament, it has attracted ...
» Read full articleFive ways to… improve agency recruitment
...improve agency recruitment 01 Plan ahead Making an agency aware of your requirements several weeks in advance will allow it to find, interview and screen local candidates well in advance of ...
» Read full article
The disability that’s coming out of hiding
Thousands of employees could be suffering from dyslexia without knowing it. But the condition is now gaining more recognition. Denise Chevin reports. Simon Hodges left school at 16. He had ...
» Read full articleFive ways to… make the most of living walls
01 Don’t be put off by the challenges of the building Living walls can go anywhere, at any height, with any aspect or level of exposure — it’s all about ...
» Read full articleRob Horne’s Case notes: June 2011
Jones v Kaney Supreme Court 2011 Most of us would not give a second thought to the consequences of someone we had asked for advice giving that advice negligently. We would ...
» Read full articleFive ways to...
Five ways to… get your green mojo back... and keep it 01 Find someone to inspire you There are plenty of green superheroes out there. Anita Roddick, Bill McKibben, Paul Hawken, Ray ...
» Read full articleInsurance at a premium
Contractors will find bonds harder to come by and the cost of professional indemnity insurance is set to rise, report David Hayhow and Jake Tobin The construction market remains slow ...
» Read full articleRefurbishment did not create a new dwelling
Court rules that couple cannot claim for defective work under the Defective Premises Act. Ben Worthington explains Builders and design consultants involved in housebuilding or refurbishment works will be interested ...
» Read full articlePaul Lomas-Clarke’case notes
De Beers UK v Atos Origin IT Services UK Technology and Construction Court 2011 Construction contracts are awash with disputes about the responsibility for delays and liability for damages. The ...
» Read full article
Measuring up to the carbon challenge
Demonstrating your sustainable credentials is easier said than done, given the number of different standards out there. But there is an alternative, says Kye Gbangbola What’s the best approach for ...
» Read full article
Green Deal’s gender agenda
Meeting carbon targets will create openings ideally suited to women, says Niki Luscombe — as long as we can train them first “Transforming the built environment to low carbon could ...
» Read full articleRichard Hildrick’s Case notes: McCain Foods GB v Eco-Tec (Europe)
McCain Foods GB v Eco-Tec (Europe) Technology and Construction Court, January 2011 In 2008, McCain entered into a £263,500 contract with Eco-Tec, which was to provide a process engineering system ...
» Read full article (1 comment)
Why we specified... April 2011
Cast in situ concrete sawtooth roof by Shepherd Construction Loughborough University Design Centre Nicholas Burwell, partner, Burwell Deakins Architects The Loughborough University Design Centre is a £15M project to construct ...
» Read full article
Why we specified...Mar11
SolarTech Renewable Energy Solutions Code Level 6 homes at Mendip Place, Chelmsford Jason Page, assistant architect, Ingleton Wood Architects At Mendip Place, six houses and four flats for local housing ...
» Read full articleGarry Winter’s Case notes – Co-operative Group v John Allen Associates
Technology and Construction Court 2010 John Allen Associates (JAA) was a consulting engineer which, while employed initially by developers, had also provided a warranty to the overall client, the Co-operative ...
» Read full articleKeeping BIM on the right side of the law
The adoption of multi-party BIM models will need careful legal underpinning. CM asked law firms Brodies and Fenwick Elliott for their views Does sharing data mean sharing liability? BIM carries on ...
» Read full articleEnvironmental markets: more detail on Defra's plans
ONLINE ONLY Bio-diversity offsetting looks like it could be arriving in the UK, following the trend in many countries to use “environmental markets” to protect natural habitats. In 2008 in the United States, conservation credits from developers raised over $3bn for wetland conservation.
» Read full article
Will pricing our wildlife ease planning pain?
The government has drawn up a proposal to let developers buy their way out of on-site biodiversity measures. Denise Chevin reports
» Read full article (1 comment)Richard Hildrick’s Case notes: February '11
Straw Realisations, formerly known as Haymills (Contractors) (in administration) v Shaftsbury House (Developments) Technology and Construction Court, October 2010 Haymills was the contractor for an £8.5m mixed-use development in Islington, ...
» Read full articleLegal update: Localism Bill explained
ONLINE ONLY By Michael Hardware of Chelgate, public relations and public affairs consultants Following much speculation as to its content, the Decentralisation and Localism Bill was finally introduced to the House of ...
» Read full articleAlisdair Matheson's Case notes: Jan '11
Dhamija & another v Sunningdale Joineries & others Technology and Construction Court, October 2010 In 2009 Mr and Mrs Dhamija pursued their contractor Sunningdale Joineries, along with their architects and ...
» Read full article (1 comment)Peter Jacobs: And about time too
Peter Jacobs, CIOB vice-president, and until recently delivery director at the 2012 Olympic Village, reviews the CIOB’s new protocol on time management. Keith Pickavance is a recent Past President of ...
» Read full article (1 comment)
Specialist cover that could be a life saver
An insurance policy that acts as an alternative to subcontractor bonds has proved popular in the US and could take off here. Elaine Knutt reports For main contractors reading the ...
» Read full article (1 comment)A tough examination
This month, two readers are concerned about the tough jobs market, despite studying to improve their chances. Our Career Consultants offer their tips. Q I am a part-time HNC Construction ...
» Read full article (3 comments)Richard Hildrick's Case notes: Nov/Dec10
How Engineering Services v Southern Insulation (Medway) Technology and Construction Court, July 2010 How Engineering was the M&E subcontractor to Sir Robert McAlpine on the development of an office building in ...
» Read full articleGarry Winter’s Case notes
Traditional Structures v H W Construction Technology and Construction Court, May 2010 H W Construction was tendering as main contractor for a business development centre. Part of the project required ...
» Read full article (1 comment)
‘Green’ clauses — the new ties that bind
As energy targets become linked to clients’ cold, hard cash, there’s a risk that new areas of loss and litigation could open up, warns Brad Fearn In our recent survey ...
» Read full articleRichard Hildrick’s Case notes
Case notes Case: WW Gear Construction v McGee Group Technology and Construction Court June 2010 WW Gear was the developer and employer for the Westminster Plaza Hotel in London. McGee ...
» Read full article (2 comments)
There’s a cloud coming your way
Outsourcing software and computer services is increasingly being seen as a cost-effective and sustainable IT option. Graham McLean advises Cloud computing is causing major shifts in the IT industry, and ...
» Read full articleCareer Consultant: What price experience?
Advice for an experienced manager who has found that a post-graduate qualification hasn’t boosted his prospects Q. I have been working in the construction industry for more than 30 years, ...
» Read full article (3 comments)Ann Wright: Computer calamity
Ann Wright’s Case notes Computer calamity Case: Kingsway Hall Hotel v Red Sky (Hounslow). Technology and Construction Court May 2010 In 2006 the Kingsway Hall Hotel paid £49,999 plus an ...
» Read full article (1 comment)Ann Wright: Summary execution
Case: Clancy Consulting v Derwent Holdings, Anglo International Holdings, Mardown, Cashtal Properties, Mount Murray Country Club and Cashtal Developments. Technology and Construction Court March 2010. The defendants were separate companies, ...
» Read full articleDo project managers make good business leaders?
A seat on the board requires different skills from project management, says Mace’s Brian Moone Excel long enough as a project manager and you may be invited to join the ...
» Read full articleAnn Wright: Insolvency isn’t always a get-out
Case: Selby Hall & Philip Shivers v Jan Van Der Heiden Technology and Construction Court, March 2010 It was a simple £143,000 flat refurb. Ms Hall and Mr Shivers hired ...
» Read full articleBaby on board
CM readers know how to manage projects, but managing your career can be a lot trickier. So we’ve assembled our panel of experienced Career Consultants to offer a fresh perspective. ...
» Read full article (2 comments)
Learning the lessons on green education
Institutions are only gradually addressing the gap in sustainable learning. Katie Puckett reports Buildings are getting more complex, regulations are tighter, and it’s increasingly down to the contractor to deliver a ...
» Read full article (6 comments)To avoid legal claims and lost tenders – read on
Under the Equality Bill, it’s time to even up pay and opportunity for everyone, writes Sharon Latham In its manifesto ahead of the 2005 general election, the Labour Party committed ...
» Read full articleAnn Wright: Questions of probability
Case: Speymill Contracts v Eric Baskind Court of Appeal February 2010 Raby House in Cheshire used to be a hotel. Sometime before 2005, it was bought by a Mr Baskind to ...
» Read full article
Get ready for next round in contractual paper chase
The new Construction Act may be on hold, but Hamish Lal says it cannot be ignored. What is the new Construction Act? When does it take effect? How will it ...
» Read full article (2 comments)The time is ripe for a new approach to insurance
At present, many contractors purchase a standard package of insurance products, regardless of the type, size, location and duration of the project. Often there are overlaps and inefficiencies with this ...
» Read full articleAnn Wright: A step in the wrong direction
Case: Thomas Henry Jose and MacSalvors Plant Hire Ltd v Brush Transformers Ltd. Court of Appeal 15 December 2009 Mr Jose, a competent and experienced crane driver, worked for plant ...
» Read full article (1 comment)
Clampdown on the framework fiddlers
New regulations have been introduced to give contractors more remedies to deal with uncompetitive practices. Peter Gracia reports After the Office of Fair Trading revelations last year that price fixing ...
» Read full articleAnn Wright: Called to account
Jim Ennis Construction Ltd v Combined Stabilisation Ltd TCC 20 November 2009 From 2008, CSL carried out groundworks for JEC at Bovis Lend Lease’s site at Unity College, Burnley. CSL’s ...
» Read full articleLegal: Blowing the whistle on construction disputes
Legal advisers suggest a range of tactics contractors can deploy to avoid or defuse disputes Many CM readers will probably have experienced the horrors of a construction dispute – if not first-hand, they’re ...
» Read full article (1 comment)


